# Saint Barnabas Hospital: asbestos abatement (320 linear ft) at 4422 Third Avenue, Bronx, starting 2026-08-17

**Score:** 30/100

| Field | Value |
|---|---|
| Owner | Saint Barnabas Hospital |
| Building | Saint Barnabas Hospital - Braker Building, 4422 Third Avenue, Bronx, 10457 |
| Building type | Hospital |
| BIN | 2094217 |
| TRU | TRU1123BX26 |
| Asbestos material | 320 linear ft |
| Abatement contractor | NSC Abatement Services, Inc |
| Air monitor | Consulting And Testing Services, Inc |
| Start | 2026-08-17 |
| End | 2027-07-30 |
| Status | Closed |

## Why this score
- Hospital.

Source: NYC Department of Environmental Protection Asbestos Control Program ACP7 project notices (data.cityofnewyork.us) (https://data.cityofnewyork.us/d/vq35-j9qm). Last refreshed: 2026-11-04T06:08:29.245Z.
From NYC DEP Asbestos Control Program ACP7 notices. Quantities and dates are as filed and are often amended or postponed; a notice is not proof work occurred. Organization-owned buildings only; unit and floor detail is not shown. Verify with NYC DEP.