# The University of Vermont Health Network - Champlain Valley Physicians Hospital: construction or renovation CON ($46,302,129), contingent approval letter sent in Plattsburgh, NY

**Score:** 75/100

| Field | Value |
|---|---|
| Facility | The University of Vermont Health Network - Champlain Valley Physicians Hospital |
| Facility type | Hospital |
| CON number | 261197 |
| Project | Construction or renovation |
| Description | Perform renovations to update the 5th, 6th, and 7th floors of the R Tower on the main campus (amends and supersedes LRA 251207) |
| Project cost | $46,302,129 |
| Review level | Admin |
| Status | Contingent Approval Letter Sent (2026-07-07) |
| Received | 2026-04-30 |
| Operator | Champlain Valley Physicians Hospital Medical Center Inc |
| Location | 75 Beekman St, Plattsburgh, Clinton County, NY |

## Why this score
- Large project budget ($46,302,129).
- Construction or renovation: buying ahead.
- Approved, construction pending.

Source: New York State Department of Health Certificate of Need Applications (health.data.ny.gov) (https://health.data.ny.gov/d/h343-jwie). Last refreshed: 2026-11-04T06:08:18.657Z.
From the NYS Department of Health Certificate of Need applications dataset. Project costs are as submitted and statuses change as DOH reviews; a filing is not an approval. Facility level only. Verify with NYS DOH (NYSE-CON).