# Consolidated Edison (Con Edison): 119 NOVs, 74 CARs on NYC street work, 2026-07-22

**Score:** 75/100

| Field | Value |
|---|---|
| Permittee | Consolidated Edison (Con Edison) |
| Permittee type | Utility or telecom |
| Inspection date | 2026-07-22 |
| NOVs | 119 |
| CARs | 74 |
| Failed re-inspections | 0 |
| Violations | Failure to obtain a confirmation number prior to expiration of DOT street opening permit (protected street) / Use/opening of street without DOT permit / Utility cover/street hardware not flush with surrounding area / Failure to obtain a confirmation number two hours prior to the commencement of a backfill on a protected street / Failure to comply with all applicable sections of the Highway Rules, the Standard Specifications, Standard Detail Drawings, and all other applicable laws or rules |
| Permit types | Non Permit; Major Install - High Voltage-Protected; Construct Or Alter Manhole &/Or Casting; Repair Electric/Communications (+23 more) |
| Streets | Bay Ridge Parkway; 148 Street; 267 Street; Hillside Avenue; Fulton Street; Pitkin Avenue (+141 more) |

## Why this score
- Corrective action request: a cut must be re-paved.
- Notice of violation issued.
- 193 findings in one day.

Source: NYC Department of Transportation street construction inspections and corrective action requests (data.cityofnewyork.us) (https://data.cityofnewyork.us/d/ydkf-mpxb). Last refreshed: 2026-11-04T21:56:41.437Z.
From NYC DOT street construction inspection data, published about monthly. A notice of violation is an allegation adjudicated at OATH and a corrective action request is a repair request; neither is a finding of fault, and outcomes are not shown. Only organizations with a legal-entity form, public bodies and utilities are shown. Verify with NYC DOT.