# Consolidated Edison (Con Edison): 40 NOVs, 16 CARs on NYC street work, 2026-09-28

**Score:** 85/100

| Field | Value |
|---|---|
| Permittee | Consolidated Edison (Con Edison) |
| Permittee type | Utility or telecom |
| Inspection date | 2026-09-28 |
| NOVs | 40 |
| CARs | 16 |
| Failed re-inspections | 0 |
| Violations | Failure to properly fasten plating and decking / Failure to replace shunt with permanent connection within 90 days / Immediately upon completion of backfill, 4 inches of temporary asphalt must be applied. / Failure to bear a sign pursuant to 34 RCNY 2-02(c)(2) with contractor's name, telephone numbers, start and end dates of all work. / Failure to permanently restore cut within required time |
| Permit types | Major Installation - Gas; Place Shunts - Streets Only; Repair Electric/Communications - Prot; Repair Gas - Protected (+15 more) |
| Streets | Mt Morris Park West; 58 Avenue; Tompkins Place; Pell Street; Merrick Boulevard; Seaview Avenue (+42 more) |

## Why this score
- Corrective action request: a cut must be re-paved.
- Notice of violation issued.
- 56 findings in one day.
- In the latest monthly release.

Source: NYC Department of Transportation street construction inspections and corrective action requests (data.cityofnewyork.us) (https://data.cityofnewyork.us/d/ydkf-mpxb). Last refreshed: 2026-11-04T21:56:41.437Z.
From NYC DOT street construction inspection data, published about monthly. A notice of violation is an allegation adjudicated at OATH and a corrective action request is a repair request; neither is a finding of fault, and outcomes are not shown. Only organizations with a legal-entity form, public bodies and utilities are shown. Verify with NYC DOT.