# Empire City Subway Company (Limited): 5 NOVs, 2 CARs on NYC street work, 2026-06-20

**Score:** 65/100

| Field | Value |
|---|---|
| Permittee | Empire City Subway Company (Limited) |
| Permittee type | Utility or telecom |
| Inspection date | 2026-06-20 |
| NOVs | 5 |
| CARs | 2 |
| Failed re-inspections | 0 |
| Violations | Failure to replace loose, slippery or broken utility maintenance hole (manhole) covers, castings, and other street hardware / Utility cover/street hardware not flush with surrounding area |
| Permit types | Non Permit; Major Installation - Telephone-Protected; Test Pits, Cores Or Boring |
| Streets | Chrystie Street; 3 Avenue; East Houston Street; 1 Avenue; Vesey Street; East 49 Street (+1 more) |

## Why this score
- Corrective action request: a cut must be re-paved.
- Notice of violation issued.
- 7 findings in one day.

Source: NYC Department of Transportation street construction inspections and corrective action requests (data.cityofnewyork.us) (https://data.cityofnewyork.us/d/ydkf-mpxb). Last refreshed: 2026-11-04T21:56:41.437Z.
From NYC DOT street construction inspection data, published about monthly. A notice of violation is an allegation adjudicated at OATH and a corrective action request is a repair request; neither is a finding of fault, and outcomes are not shown. Only organizations with a legal-entity form, public bodies and utilities are shown. Verify with NYC DOT.