# National Grid (Brooklyn Union Gas): 2 NOVs, 16 CARs on NYC street work, 2026-06-08

**Score:** 75/100

| Field | Value |
|---|---|
| Permittee | National Grid (Brooklyn Union Gas) |
| Permittee type | Utility or telecom |
| Inspection date | 2026-06-08 |
| NOVs | 2 |
| CARs | 16 |
| Failed re-inspections | 0 |
| Violations | Failure to comply with terms and conditions of DOT permit / Failure to properly fasten plating and decking |
| Permit types | Major Installation - Gas; Non Permit; Repair Gas - Protected; Tributary Install - Gas - Protected (+4 more) |
| Streets | De Kalb Avenue; 3 Avenue; Crescent Street; 72 Street; Purdue Street; Forest Street (+11 more) |

## Why this score
- Corrective action request: a cut must be re-paved.
- Notice of violation issued.
- 18 findings in one day.

Source: NYC Department of Transportation street construction inspections and corrective action requests (data.cityofnewyork.us) (https://data.cityofnewyork.us/d/ydkf-mpxb). Last refreshed: 2026-11-04T21:56:41.437Z.
From NYC DOT street construction inspection data, published about monthly. A notice of violation is an allegation adjudicated at OATH and a corrective action request is a repair request; neither is a finding of fault, and outcomes are not shown. Only organizations with a legal-entity form, public bodies and utilities are shown. Verify with NYC DOT.