# National Grid (Brooklyn Union Gas): 9 NOVs, 11 CARs on NYC street work, 2026-09-04

**Score:** 75/100

| Field | Value |
|---|---|
| Permittee | National Grid (Brooklyn Union Gas) |
| Permittee type | Utility or telecom |
| Inspection date | 2026-09-04 |
| NOVs | 9 |
| CARs | 11 |
| Failed re-inspections | 0 |
| Violations | Binder base or temporary restoration not flush with surrounding area / Failure to comply with terms and conditions of DOT permit / Failure to obtain a confirmation number two hours prior to the commencement of a backfill on a protected street / Immediately upon completion of backfill, 4 inches of temporary asphalt must be applied. / Obstruction of any portion of street with construction materials/equipment without DOT permit |
| Permit types | Major Installation - Gas; Repair Gas - Protected; Tributary Install - Gas - Protected; Major Installations - Gas-Protected (+3 more) |
| Streets | Wheeler Avenue; Caroline Street; Fountain Avenue; Myrtle Avenue; Bay 32 Street; Castleton Avenue (+10 more) |

## Why this score
- Corrective action request: a cut must be re-paved.
- Notice of violation issued.
- 20 findings in one day.

Source: NYC Department of Transportation street construction inspections and corrective action requests (data.cityofnewyork.us) (https://data.cityofnewyork.us/d/ydkf-mpxb). Last refreshed: 2026-10-28T20:51:30.518Z.
From NYC DOT street construction inspection data, published about monthly. A notice of violation is an allegation adjudicated at OATH and a corrective action request is a repair request; neither is a finding of fault, and outcomes are not shown. Only organizations with a legal-entity form, public bodies and utilities are shown. Verify with NYC DOT.