# High Dam Hydroelectric Facility: 9.2 MW hydroelectric project, operational in Oswego County, NY

**Score:** 25/100

| Field | Value |
|---|---|
| Project | High Dam Hydroelectric Facility |
| Developer | City of Oswego |
| Technology | Hydroelectric |
| Capacity | 9.2 MW |
| Solicitation | RESRFP25-1 |
| Status | Operational |
| Delivery start | 2026 |
| Permit process | Other |
| NYISO zone | Central |
| Location | Oswego County, NY |
| Data through | 2026-09-30 |

## Why this score
- Delivery starts 2026.

Source: NYSERDA Large-scale Renewable Projects Reported by NYSERDA: Beginning 2004 (data.ny.gov) (https://data.ny.gov/d/dprp-55ye). Last refreshed: 2026-10-28T20:50:36.276Z.
From NYSERDA's Large-scale Renewable Projects dataset, refreshed quarterly. Capacity and dates are contract figures; projects under development may be delayed or cancelled. Project level only. Verify with NYSERDA and the NYS DPS.