# Valcour Chateaugay Windpark: 87.63 MW land-based wind project, under development in Clinton County, NY

**Score:** 75/100

| Field | Value |
|---|---|
| Project | Valcour Chateaugay Windpark |
| Developer | AES Corporation |
| Technology | Land-based Wind |
| Capacity | 87.63 MW |
| Solicitation | RESRFP22-1 |
| Status | Under Development |
| Delivery start | 2029 |
| Permit process | ORES |
| Interconnection queue # | 214 |
| NYISO zone | North |
| Location | Clinton County, NY |
| Data through | 2026-09-30 |

## Why this score
- Under development: construction, equipment and financing ahead.
- 87.63 MW.
- Delivery starts 2029.

Source: NYSERDA Large-scale Renewable Projects Reported by NYSERDA: Beginning 2004 (data.ny.gov) (https://data.ny.gov/d/dprp-55ye). Last refreshed: 2026-11-04T21:51:16.250Z.