# Accord Power Inc: 46 kW commercial solar installed in Bronx, Bronx County, NY (completed 2026-06-24)

**Score:** 50/100

| Field | Value |
|---|---|
| Installer / developer | Accord Power Inc |
| Project type | Commercial solar (small commercial program) |
| Stage | Installed / completed |
| Applied / approved | 2025-05-08 |
| Completed | 2026-06-24 |
| Location | Bronx, Bronx County, NY |
| Utility | Consolidated Edison |
| Size | 46 kW |
| Project cost | $138,600 |
| NYSERDA incentive | $27,390 |
| Program | Residential/Small Commercial, PON 2112 |
| Ownership | Purchase |
| Module maker | Boviet Solar Technology Co., Ltd. |
| Inverter maker | SolarEdge Technologies Ltd. |
| NYSERDA project number | 0000916902 |

## Why this score
- Just completed: O&M and monitoring needed.
- Project cost over $100K.
- Installer named.

Source: NYSERDA Solar Electric Programs and Residential, Retail and Bulk Energy Storage Incentive Programs (data.ny.gov) (https://data.ny.gov/d/3x8r-34rs). Last refreshed: 2026-10-28T20:50:28.420Z.
From NYSERDA program data, published monthly. Pipeline projects may change size, be cancelled or never be built; costs and incentives are as reported to NYSERDA. Residential projects and host-site street addresses are excluded. Verify with NYSERDA or the installer.