# 3lw Civil LLC: TxDOT bridge replacement contract 97% complete, CR, Lavaca County ($1,559,732, 4 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | 3lw Civil LLC |
| Subcontractors | Lone Star Paving Company (4.7%); Hermanos Steel, LLC (0.16%); Highway Barricades And Services, LLC (0.6%); Gregory Pile Driving, INC. (12.88%) |
| Progress | 96.69% complete, 81.87% of time used |
| Amount | $1,559,732 revised (original $1,541,729) |
| Paid to date | $1,490,735 |
| Work | Bridge Replacement |
| Location | CR, CR 130 AT RICKAWAY BRANCH to STR# AA05-61-001, Lavaca County, Yoakum District |
| Let / began | 2025-07-02 / 2025-12-09 |
| Latest estimate | 2026-10-05 |
| Contract number | 7253225 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.