# 3lw Civil LLC: TxDOT hazard elimination & safety contract 80% complete, FM 855, Cherokee County ($4,139,164, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | 3lw Civil LLC |
| Subcontractors | Cap River LLC (3.55%); Diamond Elite Barricades, LLC (0.44%); Striping Technology, L.P. (3.19%); Grider Paving LLC (1.05%) |
| Progress | 80.19% complete, 94.76% of time used |
| Amount | $4,139,164 revised (original $4,101,439) |
| Change orders | $34,725 |
| Paid to date | $3,316,764 |
| Work | Hazard Elimination & Safety |
| Location | FM 855, US 69 to US 175, Cherokee County, Tyler District |
| Let / began | 2025-08-08 / 2025-10-15 |
| Latest estimate | 2026-10-02 |
| Contract number | 8253205 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.