# A. K. Gillis & Sons, LLC: TxDOT rehabilitation of existing road contract 90% complete, FM 547, Collin County ($17,299,208, 11 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | A. K. Gillis & Sons, LLC |
| Subcontractors | Stripe-A-Zone, LLC (0.74%); Bahena Construction Co., INC. (10.5%); Catocon, INC. (0.38%); Marcoms Construction LLC (0.56%); Rk Hall, LLC (22.69%); Surface Preparation Technologies, LLC (0.15%); Texop Construction (1.11%); Traffic Highway Maintenance, LLC (0.74%); Texas Traffic And Barricade, LLC (0.15%); (Inactive)site Barricades (0.15%); Southern Cross Contractors, LLC (0.24%) |
| Progress | 89.85% complete, 93.7% of time used |
| Amount | $17,299,208 revised (original $16,422,403) |
| Change orders | $416,804 |
| Paid to date | $15,130,341 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 547, FM 6 to US 380, Collin County, Dallas District |
| Let / began | 2025-05-02 / 2025-07-14 |
| Latest estimate | 2026-10-05 |
| Contract number | 5253202 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.