# A. K. Gillis & Sons, LLC: TxDOT rehabilitation of existing road contract 95% complete, FM 2120, Red River County ($9,932,732, 7 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | A. K. Gillis & Sons, LLC |
| Subcontractors | Withers Construction, LLC (7.3%); Striping Technology, L.P. (2.93%); Southern Cross Contractors, LLC (0.84%); Panola Sign & Barricade, INC. (0.49%); A. E. Moore Construction, INC. (2.69%); Bahena Construction Co., INC. (5.45%); Anchor Contracting, LLC (0.64%) |
| Progress | 95.04% complete, 92.35% of time used |
| Amount | $9,932,732 revised (original $9,798,191) |
| Change orders | $38,866 |
| Paid to date | $9,349,109 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 2120, FM 2120 FROM FM 2573 TO CR 2235; FROM CR 2235 TO SH 37, Red River County, Paris District |
| Let / began | 2023-06-27 / 2023-10-24 |
| Latest estimate | 2026-10-05 |
| Contract number | 6233415 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.