# A. K. Gillis & Sons, LLC: TxDOT rehabilitation of existing road contract 99% complete, FM 2645, Fannin County ($7,652,012, 8 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | A. K. Gillis & Sons, LLC |
| Subcontractors | Rk Hall, LLC (26.02%); Advanced Barricades Of America, LLC (0.37%); Withers Construction, LLC (1.7%); Bahena Construction Co., INC. (8.08%); Dustin Allen, INC. (0.7%); West Texas Rock Resources, LLC (0.37%); Southern Cross Contractors, LLC (0.58%); Striping Technology, L.P. (1.77%) |
| Progress | 99.03% complete, 93.14% of time used |
| Amount | $7,652,012 revised (original $7,274,667) |
| Change orders | $-33,397 |
| Paid to date | $7,171,364 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 2645, FM 2645 FROM FM 898 TO FM 1753, Fannin County, Paris District |
| Let / began | 2024-06-05 / 2024-09-04 |
| Latest estimate | 2026-10-05 |
| Contract number | 6243011 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.