# A. K. Gillis & Sons, LLC: TxDOT hazard elimination & safety contract 77% complete, FM 1138, Collin County ($7,996,047, 11 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | A. K. Gillis & Sons, LLC |
| Subcontractors | Catocon, INC. (0.23%); Advanced Barricades Of America, LLC (0.16%); Bahena Construction Co., INC. (7.59%); Dustin Allen, INC. (0.17%); Ibctx, LLC (8.16%); J. H. Oden Contracting Company (2.27%); Southern Cross Contractors, LLC (0.21%); Surface Preparation Technologies, LLC (0.14%); Striping Technology, L.P. (0.76%); Texop Construction (1.6%); Overland Corporation (27.01%) |
| Progress | 76.66% complete, 88.53% of time used |
| Amount | $7,996,047 revised (original $7,635,941) |
| Change orders | $31,106 |
| Paid to date | $5,877,288 |
| Work | Hazard Elimination & Safety |
| Location | FM 1138, NORTH OF W COUNTY LINE ROAD to W COUNTY LINE ROAD, Collin County, Dallas District |
| Let / began | 2025-08-07 / 2025-09-29 |
| Latest estimate | 2026-10-05 |
| Contract number | 8253003 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.