# A. L. Helmcamp, INC.: TxDOT widen non-freeway contract 64% complete, US 175, Cherokee County ($171,724,922, 15 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | Isaacs Construction Services LLC (0%); 4m Construction Services, INC. (0.3%); Baker & Company Construction, LLC (3.92%); Big Creek Construction, LTD. (26.5%); Fortson Contracting, INC. (0.17%); Hermanos Steel, LLC (0.12%); Jm Yanez Construction, INC. (1.08%); Murray Construction (0.11%); Panola Sign & Barricade, INC. (0.18%); Primate Construction, LP (0.02%); Southwest Environment Services LLC (2.45%); Striping Technology, L.P. (0.52%); Surface Preparation Technologies, LLC (0.01%); J. H. Oden Contracting Company (0%); Oscar Orduno, INC. (0.06%) |
| Progress | 63.76% complete, 55.97% of time used |
| Amount | $171,724,922 revised (original $167,154,897) |
| Change orders | $2,669,728 |
| Paid to date | $108,277,497 |
| Work | Widen Non-Freeway |
| Location | US 175, 0.5 MI E OF ANDERSON C/L(CR3509),SE to FM 347, IN JACKSONVILLE, Cherokee County, Tyler District |
| Let / began | 2023-10-05 / 2024-01-19 |
| Latest estimate | 2026-10-02 |
| Contract number | 10233001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.