# A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 27% complete, SH 137, Terry County ($22,831,736, 7 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | Fc Traffic Control, INC. (0.13%); J. H. Oden Contracting Company (0.39%); Marcoms Construction LLC (0.57%); W. S. Construction Company (2.85%); Surface Preparation Technologies, LLC (0.16%); Trp Construction Group, LLC (3.11%); Industrial Fabrics, INC. (8.58%) |
| Progress | 27.18% complete, 79.29% of time used |
| Amount | $22,831,736 revised (original $22,303,962) |
| Change orders | $268,083 |
| Paid to date | $6,134,095 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 137, BROWNFIELD to DAWSON, Terry County, Lubbock District |
| Let / began | 2025-10-09 / 2026-01-19 |
| Latest estimate | 2026-10-06 |
| Contract number | 10253202 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.