# A. L. Helmcamp, INC.: TxDOT maintenance contract 93% complete, FM0145, Castro County ($2,288,505)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Progress | 93.44% complete, 100% of time used |
| Amount | $2,288,505 revised (original $2,282,170) |
| Change orders | $6,335 |
| Paid to date | $2,138,373 |
| Work | Maintenance |
| Location | FM0145, INTERSECTION OF FM145 & SH194 (HART to CASTRO/SWISHER COUNTY LINE, Castro County, Lubbock District |
| Let / began | 2025-12-02 / 2026-04-13 |
| Latest estimate | 2026-10-05 |
| Contract number | 12254001 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.