# A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 93% complete, US 380, Jack County ($19,391,502, 8 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | Cold Creek Construction, LTD (0.46%); J. H. Oden Contracting Company (4.14%); Marcoms Construction LLC (0.27%); Mobile Enterprises, INC. (0.07%); Roadway Specialties, INC. (0.88%); Surface Preparation Technologies, LLC (0.11%); Traffic Highway Maintenance, LLC (1.59%); W. S. Construction Company (10.26%) |
| Progress | 92.74% complete, 129.9% of time used |
| Amount | $19,391,502 revised (original $18,488,019) |
| Change orders | $321,639 |
| Paid to date | $17,444,397 |
| Work | Rehabilitation Of Existing Road |
| Location | US 380, FM 1156 to WISE COUNTY LINE, Jack County, Fort Worth District |
| Let / began | 2024-02-02 / 2024-07-22 |
| Latest estimate | 2026-10-05 |
| Contract number | 2243206 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.