# A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 99% complete, FM 1450, Reeves County ($81,708,506, 9 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | Wild West Trucking, LLC (1.64%); A.L. Construction LLC (1.01%); Texas Environmental Management - San Antonio, INC. (0.17%); Willis Electric Co., LP (0.48%); Double A Contracting, L.P. (0.77%); Fc Traffic Control, INC. (0.17%); Marcom's Mowing Service, LLC (0.18%); Hjc Farms, INC. (0.02%); A Brothers Milling, LLC (0.18%) |
| Progress | 99.03% complete, 100% of time used |
| Amount | $81,708,506 revised (original $81,336,502) |
| Change orders | $-1,008,173 |
| Paid to date | $79,550,380 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 1450, 8 M E of US285 to FM1776, Reeves County, Odessa District |
| Let / began | 2023-03-07 / 2023-09-05 |
| Latest estimate | 2026-09-30 |
| Contract number | 3233002 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.