# A. L. Helmcamp, INC.: TxDOT overlay contract 94% complete, US 84, Garza County ($13,430,032, 7 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | A Brothers Milling, LLC (1.24%); Dustin Allen, INC. (1.72%); Marcoms Construction LLC (0.22%); Double A Contracting, L.P. (2.05%); Industrial Fabrics, INC. (0.96%); J. H. Oden Contracting Company (1.46%); W. S. Construction Company (0.64%) |
| Progress | 93.69% complete, 107.87% of time used |
| Amount | $13,430,032 revised (original $13,312,185) |
| Change orders | $19,847 |
| Paid to date | $12,490,347 |
| Work | Overlay |
| Location | US 84, FM 2458 to SCURRY COUNTY LINE, Garza County, Lubbock District |
| Let / began | 2025-03-04 / 2025-07-16 |
| Latest estimate | 2026-10-06 |
| Contract number | 3253004 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.