# A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 73% complete, US 87, Dawson County ($15,149,647, 8 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | W. S. Construction Company (4.42%); A Brothers Milling, LLC (0.56%); Apollo Constructors, INC. (5.64%); Hjc Farms, INC. (0.67%); Industrial Fabrics, INC. (1.21%); Surface Preparation Technologies, LLC (0.12%); Trp Construction Group, LLC (2.77%); Jvh4 Services, LLC (0.23%) |
| Progress | 73.42% complete, 92.8% of time used |
| Amount | $15,149,647 revised (original $14,793,665) |
| Change orders | $48,710 |
| Paid to date | $10,897,861 |
| Work | Rehabilitation Of Existing Road |
| Location | US 87, 0.5 MILES NORTH OF US 349 to 0.5 MILES SOUTH OF US 349, Dawson County, Lubbock District |
| Let / began | 2024-04-04 / 2025-01-06 |
| Latest estimate | 2026-10-06 |
| Contract number | 4243041 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.