# A. L. Helmcamp, INC.: TxDOT bridge replacement contract 38% complete, FM 324, Angelina County ($27,453,785, 12 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | H4 Construction Services, LLC (0.28%); Batterson, LLP (0.3%); A R Brothers Construction Services, INC. (2.18%); Cen Tex Hydroseed, INC. (0.53%); Southwest Road & Safety Contractors, LTD. (0.52%); Hermanos Steel, LLC (0.63%); Jb Pinnacle Group, LLC (1.43%); Panola Sign & Barricade, INC. (0.15%); Primate Construction, LP (0.1%); Surface Preparation Technologies, LLC (0.04%); Creacom, INC. (0.48%); Cold Creek Construction, LTD (0.57%) |
| Progress | 38.14% complete, 52.63% of time used |
| Amount | $27,453,785 revised (original $27,229,475) |
| Change orders | $180,610 |
| Paid to date | $10,454,150 |
| Work | Bridge Replacement |
| Location | FM 324, AT HURRICANE CREEK, Angelina County, Lufkin District |
| Let / began | 2025-04-03 / 2025-09-18 |
| Latest estimate | 2026-10-05 |
| Contract number | 4253003 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.