# A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 41% complete, FM 2727, Kaufman County ($17,212,280, 7 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | A.L. Construction LLC (3.35%); Cold Creek Construction, LTD (0.46%); Dustin Allen, INC. (0.39%); Marcoms Construction LLC (0.62%); Panola Sign & Barricade, INC. (0.25%); Trp Construction Group, LLC (0.92%); Wolfe Construction Group, Incorporated (0.71%) |
| Progress | 41.36% complete, 57.85% of time used |
| Amount | $17,212,280 revised (original $16,864,509) |
| Change orders | $216,770 |
| Paid to date | $7,064,789 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 2727, SH 243 to FM 429, Kaufman County, Dallas District |
| Let / began | 2025-04-03 / 2025-07-14 |
| Latest estimate | 2026-10-02 |
| Contract number | 4253004 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.