# A. L. Helmcamp, INC.: TxDOT bridge replacement contract 99% complete, SH 174, Hill County ($22,835,358, 13 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | Fortson Contracting, INC. (0.9%); Hermanos Steel, LLC (0.4%); Highway Traffic Control & Services, LLC (0.12%); Hunter Demolition & Wrecking Corporation (6.18%); Primate Construction, LP (0.06%); Roadway Specialties, INC. (0.08%); Striping Technology, L.P. (0.32%); Wolfe Construction Group, Incorporated (0.37%); Bear Creek Construction, LLC (0.54%); Farr Foundation, INC. (0.07%); West Texas Rumble Strip LLC (0.02%); A Brothers Milling, LLC (0.06%); H4 Construction Services, LLC (0.17%) |
| Progress | 98.64% complete, 179.87% of time used |
| Amount | $22,835,358 revised (original $23,690,787) |
| Change orders | $-855,429 |
| Paid to date | $22,525,103 |
| Work | Bridge Replacement |
| Location | SH 174, @ BRAZOS RIVER_(LAKE WHITNEY) to (STR #005), Hill County, Waco District |
| Let / began | 2022-05-05 / 2022-11-01 |
| Latest estimate | 2026-10-01 |
| Contract number | 5223206 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.