# A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 20% complete, US 70, Parmer County ($31,056,773, 10 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | Apollo Constructors, INC. (1.01%); Fc Traffic Control, INC. (0.31%); Hjc Farms, INC. (13.43%); J. H. Oden Contracting Company (0.29%); Industrial Fabrics, INC. (6.77%); Marcoms Construction LLC (0.74%); Surface Preparation Technologies, LLC (0.09%); Trp Construction Group, LLC (2.96%); W. S. Construction Company (1.57%); A Brothers Milling, LLC (0.99%) |
| Progress | 19.81% complete, 57.23% of time used |
| Amount | $31,056,773 revised (original $29,652,485) |
| Paid to date | $5,874,826 |
| Work | Rehabilitation Of Existing Road |
| Location | US 70, FARWELL CITY LIMITS to BAILEY COUNTY LINE, Parmer County, Lubbock District |
| Let / began | 2025-05-01 / 2025-11-13 |
| Latest estimate | 2026-10-06 |
| Contract number | 5253002 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.