# A. L. Helmcamp, INC.: TxDOT widen non-freeway contract 35% complete, SH 36, Taylor County ($11,585,486, 11 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | Nelson Industrial Services, INC. (0.13%); Gibson & Associates, INC. (2.38%); Flat Line, INC. (1.63%); Hjc Farms, INC. (0.93%); 4-Way Haulers, LLC (6.87%); Fc Traffic Control, INC. (0.26%); Willis Electric Co., LP (1.1%); Wolfe Construction Group, Incorporated (0.74%); Murray Construction (0.93%); Cold Creek Construction, LTD (0.27%); Surface Preparation Technologies, LLC (0.16%) |
| Progress | 34.56% complete, 55.28% of time used |
| Amount | $11,585,486 revised (original $10,612,471) |
| Paid to date | $3,668,017 |
| Work | Widen Non-Freeway |
| Location | SH 36, CR 123 to CALLAHAN COUNTY, Taylor County, Abilene District |
| Let / began | 2025-05-02 / 2025-09-29 |
| Latest estimate | 2026-10-06 |
| Contract number | 5253203 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.