# A. L. Helmcamp, INC.: TxDOT widen non-freeway contract 61% complete, SH 25, Wichita County ($20,591,832, 7 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | Flat Line, INC. (0.91%); W. S. Construction Company (11.18%); Dustin Allen, INC. (0.5%); Lanco Turf & Seeding, INC. (1.28%); Marcoms Construction LLC (0.61%); Fc Traffic Control, INC. (0.18%); Surface Preparation Technologies, LLC (0.21%) |
| Progress | 60.77% complete, 72.05% of time used |
| Amount | $20,591,832 revised (original $20,570,032) |
| Paid to date | $12,500,648 |
| Work | Widen Non-Freeway |
| Location | SH 25, FM 1811 to ARCHER COUNTY LINE, Wichita County, Wichita Falls District |
| Let / began | 2024-06-05 / 2024-08-29 |
| Latest estimate | 2026-10-02 |
| Contract number | 6243008 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.