# A. L. Helmcamp, INC.: TxDOT widen freeway contract 44% complete, US 82, Montague County ($40,029,127, 12 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | Toro Bravo Construction, LLC (0.02%); Mica Corporation (1.02%); Mobile Enterprises, INC. (0.04%); Trp Construction Group, LLC (0.84%); Marcoms Construction LLC (0.37%); Coppell Construction Co., INC. (9.65%); Hodges And Son Construction Company, INC. (0.65%); J. H. Oden Contracting Company (1.5%); W. S. Construction Company (10.91%); Southern Cross Contractors, LLC (0.81%); Penhall Company (0.05%); Kingsley Constructors, INC. (1.18%) |
| Progress | 44.14% complete, 65.3% of time used |
| Amount | $40,029,127 revised (original $38,961,339) |
| Change orders | $834,428 |
| Paid to date | $17,565,657 |
| Work | Widen Freeway |
| Location | US 82, CLAY COUNTY LINE to APPROX 0.5 MI. E OF US 81 (RINGGOLD, Montague County, Wichita Falls District |
| Let / began | 2024-06-06 / 2024-11-11 |
| Latest estimate | 2026-10-01 |
| Contract number | 6243205 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.