# A. L. Helmcamp, INC.: TxDOT widen non-freeway contract 19% complete, FM 2185, Culberson County ($123,817,484, 7 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | Penhall Company (0.04%); Ancortex, INC. (0.43%); Toro Bravo Construction, LLC (0.26%); J. H. Oden Contracting Company (0.27%); Cold Creek Construction, LTD (0.32%); Marcoms Construction LLC (0.11%); Buckley Powder Co (0.3%) |
| Progress | 18.91% complete, 27.07% of time used |
| Amount | $123,817,484 revised (original $123,682,484) |
| Paid to date | $23,394,541 |
| Work | Widen Non-Freeway |
| Location | FM 2185, 750 FEET SOUTH OF LOONEY SPUR ROAD to JUNCTION WITH FM 3541, Culberson County, El Paso District |
| Let / began | 2025-06-04 / 2026-01-05 |
| Latest estimate | 2026-10-02 |
| Contract number | 6253001 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.