# A. L. Helmcamp, INC.: TxDOT rehabilitation of existing road contract 96% complete, FM 2930, Navarro County ($13,089,489, 11 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | Bear Creek Construction, LLC (22.21%); Texas Environmental Management - San Antonio, INC. (0.46%); USA Swppp Inspections, INC. (2.07%); Murray Construction (0.48%); Stripe-A-Zone, LLC (1.35%); Cold Creek Construction, LTD (0.62%); Fortson Contracting, INC. (2.28%); H4 Construction Services, LLC (0.95%); Texas Traffic And Barricade, LLC (0.14%); Cdm Holdings (0.33%); (Inactive)site Barricades (0.14%) |
| Progress | 96.23% complete, 98.34% of time used |
| Amount | $13,089,489 revised (original $11,334,815) |
| Change orders | $1,598,874 |
| Paid to date | $12,446,262 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 2930, FM 55 EAST to FM 1126 NORTH IN CRYER CREEK, Navarro County, Dallas District |
| Let / began | 2023-08-02 / 2023-11-27 |
| Latest estimate | 2026-10-05 |
| Contract number | 8233007 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.