# A. L. Helmcamp, INC.: TxDOT hazard elimination & safety contract 42% complete, SH 198, Kaufman County ($5,472,211, 8 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | A. L. Helmcamp, INC. |
| Subcontractors | Trp Construction Group, LLC (0.77%); Wolfe Construction Group, Incorporated (0.92%); Panola Sign & Barricade, INC. (0.23%); Marcoms Construction LLC (0.4%); Dustin Allen, INC. (1.83%); Cold Creek Construction, LTD (1.04%); Bahena Construction Co., INC. (12.98%); H4 Construction Services, LLC (27.54%) |
| Progress | 41.83% complete, 74.06% of time used |
| Amount | $5,472,211 revised (original $5,180,452) |
| Change orders | $235,759 |
| Paid to date | $2,265,541 |
| Work | Hazard Elimination & Safety |
| Location | SH 198, NORTH OF US 175 to FM 3080, Kaufman County, Dallas District |
| Let / began | 2025-08-07 / 2025-11-10 |
| Latest estimate | 2026-10-02 |
| Contract number | 8253007 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.