# Aad Contracting INC.: TxDOT bridge widening or rehabilitation contract 100%+ complete, BU 82J, Red River County ($748,396, 5 subs)

**Score:** 45/100

| Field | Value |
|---|---|
| Prime contractor | Aad Contracting INC. |
| Subcontractors | Skidabrader Group LLC (1.02%); Dallas Lite And Barricade, INC. (2.71%); Straight Line Sawing & Sealing, INC. (2.59%); Richard Drake Construction Company, L.P. (10.51%); Texop Construction (2.12%) |
| Progress | 102.77% complete, 100% of time used |
| Amount | $748,396 revised (original $627,372) |
| Change orders | $106,278 |
| Paid to date | $754,001 |
| Work | Bridge Widening Or Rehabilitation |
| Location | BU 82J, BU 82J-AT E LANGFORD, AT S BIG, AT BRUTON, AT SCATTER CREEKS, Red River County, Paris District |
| Let / began | 2024-02-02 / 2024-06-13 |
| Latest estimate | 2026-10-05 |
| Contract number | 2243238 |

## Why this score
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.