# Aad Contracting INC.: TxDOT hazard elimination & safety contract 81% complete, BU 82J, Red River County ($1,504,670, 3 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Aad Contracting INC. |
| Subcontractors | A. E. Moore Construction, INC. (3.38%); Keystone Foundation Repair INC. (13.5%); Wg Engineering & Construction, LLC (2.73%) |
| Progress | 81.38% complete, 121.52% of time used |
| Amount | $1,504,670 revised (original $1,486,446) |
| Change orders | $-37,710 |
| Paid to date | $1,178,942 |
| Work | Hazard Elimination & Safety |
| Location | BU 82J, BU 82J FROM SH 37 TO N HIGH ST, Red River County, Paris District |
| Let / began | 2025-02-07 / 2025-05-29 |
| Latest estimate | 2026-10-05 |
| Contract number | 2253227 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.