# Aaron Concrete Contractors, LLC: TxDOT hazard elimination & safety contract 26% complete, FM 3405, Williamson County ($2,927,951, 5 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Aaron Concrete Contractors, LLC |
| Subcontractors | Trp Construction Group, LLC (0.66%); King Kong Concrete Co LLC (2.93%); D. I. J. Construction, INC. (4.38%); Environmental Safety Services, INC. (11.41%); Lone Star Paving Company (33.62%) |
| Progress | 26.06% complete, 54.81% of time used |
| Amount | $2,927,951 revised (original $2,760,448) |
| Paid to date | $719,464 |
| Work | Hazard Elimination & Safety |
| Location | FM 3405, 0.348 MI E OF RONALD REAGAN BLVD to 0.228 MI W OF GEORGETOWN HEIGHTS DR, Williamson County, Austin District |
| Let / began | 2026-02-05 / 2026-06-04 |
| Latest estimate | 2026-10-05 |
| Contract number | 2263214 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.