# Abescape Group LLC: TxDOT maintenance contract 87% complete, SH0208, Tom Green County ($202,170)

**Score:** 25/100

| Field | Value |
|---|---|
| Prime contractor | Abescape Group LLC |
| Progress | 86.7% complete, 140.38% of time used |
| Amount | $202,170 revised (original $184,808) |
| Change orders | $17,364 |
| Paid to date | $175,286 |
| Work | Maintenance |
| Location | SH0208, VARIOUS HIGHWAYS IN TOM GREEN COUNT, Tom Green County, San Angelo District |
| Let / began | 2025-12-09 / 2026-01-12 |
| Latest estimate | 2026-10-02 |
| Contract number | 12250701 |

## Why this score


Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.