# Acme Bridge Company, INC.: TxDOT widen non-freeway contract 100%+ complete, RM 473, Kendall County ($4,459,611, 7 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Acme Bridge Company, INC. |
| Subcontractors | Trp Construction Group, LLC (4.22%); Murray Construction (2.42%); Eggemeyer Land Clearing, LLC (1.47%); Diibs Specialists, LLC (1.25%); South Texas Traffic Alliance INC. (0.52%); J. H. Oden Contracting Company (7.37%); Mpb, INC. (5.15%) |
| Progress | 103.05% complete, 92.93% of time used |
| Amount | $4,459,611 revised (original $4,477,119) |
| Change orders | $-17,508 |
| Paid to date | $4,595,431 |
| Work | Widen Non-Freeway |
| Location | RM 473, OLD NO. 9 HWY to RM 1376, Kendall County, San Antonio District |
| Let / began | 2024-07-10 / 2024-10-07 |
| Latest estimate | 2026-10-05 |
| Contract number | 7243208 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.