# Acme Bridge Company, INC.: TxDOT bridge replacement contract 53% complete, US 77, Lee County ($13,511,601, 14 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Acme Bridge Company, INC. |
| Subcontractors | Jb Pinnacle Group, LLC (0.88%); 4e Tree Worx LLC (0.34%); Gk Construction, LLC (0.56%); Capstar Construction, LLC (0.91%); Dustrol, INC. (0.15%); Superior Traffic Control, LLC (0.12%); Farr Foundation, INC. (4.7%); (Inactive)stripe It Up, LLC (0.19%); Primate Construction, LP (0.08%); Rhino Equity, LLC (1.6%); Lone Star Paving Company (3.58%); Hodges And Son Construction Company, INC. (3.7%); Toro Bravo Construction, LLC (0%); A K Fuquay Construction (0.09%) |
| Progress | 52.86% complete, 60.92% of time used |
| Amount | $13,511,601 revised (original $13,219,085) |
| Change orders | $71,072 |
| Paid to date | $7,024,561 |
| Work | Bridge Replacement |
| Location | US 77, 0.10 MILES SOUTH OF N. JAEGER STREE to STR # 14-144-0-0211-07-048, Lee County, Austin District |
| Let / began | 2025-08-07 / 2026-01-14 |
| Latest estimate | 2026-10-05 |
| Contract number | 8253028 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.