# Allen Keller Company: TxDOT rehabilitation of existing road contract 82% complete, FM 45, Mills County ($32,777,188, 15 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Allen Keller Company |
| Subcontractors | Delgado's Contractors, LLC (24.53%); Toro Bravo Construction, LLC (0.33%); Prater Dirt Work LLC (0.84%); 4e Tree Worx LLC (0.08%); Erfurt Blasting Company, INC. (1.68%); Dk Contracting, LLC (0.26%); Professional Traffic Control LLC (0.04%); Rpv Construction, LLC (1.27%); D. I. J. Construction, INC. (1.63%); Aaron Concrete Contractors, LLC (0%); Royal Rebar INC (0%); Keller Trucking, INC. (0.25%); A K Fuquay Construction (1.4%); Primate Construction, LP (0%); Sk Concrete Services LLC (0%) |
| Progress | 81.86% complete, 87.25% of time used |
| Amount | $32,777,188 revised (original $32,511,818) |
| Change orders | $-443,217 |
| Paid to date | $26,250,374 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 45, MILLS C/L to FM 502, Mills County, Brownwood District |
| Let / began | 2024-06-05 / 2024-09-09 |
| Latest estimate | 2026-09-30 |
| Contract number | 6243006 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.