# Allen Keller Company: TxDOT rehabilitation of existing road contract 44% complete, SH 29, Burnet County ($11,057,183, 5 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Allen Keller Company |
| Subcontractors | D. I. J. Construction, INC. (2.01%); Environmental Safety Services, INC. (7.11%); Mpb, INC. (14.96%); 4e Tree Worx LLC (1%); Tech Con Trenching, INC. (0.72%) |
| Progress | 44.23% complete, 43.19% of time used |
| Amount | $11,057,183 revised (original $10,701,288) |
| Change orders | $172,892 |
| Paid to date | $4,809,471 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 29, 0.382 MI W OF ALGERITA HILL RD to LEHNE RD, Burnet County, Austin District |
| Let / began | 2025-08-08 / 2025-11-17 |
| Latest estimate | 2026-10-05 |
| Contract number | 8253203 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.