# Allstate Signal & Construction, LLC: TxDOT traffic signal contract 77% complete, US 290, Waller County ($11,667,435, 2 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Allstate Signal & Construction, LLC |
| Subcontractors | Bay City Traffic (3.27%); Willow City Sign & Rail, INC. (1.63%) |
| Progress | 76.86% complete, 47.06% of time used |
| Amount | $11,667,435 revised (original $11,686,064) |
| Change orders | $-172,630 |
| Paid to date | $8,849,456 |
| Work | Traffic Signal |
| Location | US 290, WASHINGTON COUNTY LINE to HARRIS COUNTY LINE, Waller County, Houston District |
| Let / began | 2025-04-04 / 2025-12-18 |
| Latest estimate | 2026-09-30 |
| Contract number | 4253205 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.