# Altus Construction LLC: TxDOT bridge replacement contract 93% complete, SH 25, Archer County ($6,523,856, 9 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Altus Construction LLC |
| Subcontractors | Texop Construction (0.49%); Peachtree Construction, LTD. (10%); West Texas Rumble Strip LLC (0.2%); Trp Construction Group, LLC (1.55%); Toro Bravo Construction, LLC (0.86%); Square Contracting INC (9.48%); S & S Bridge Painting, INC. (1.02%); Hodges And Son Construction Company, INC. (2.96%); Emery Sapp & Son's INC. (0.31%) |
| Progress | 92.5% complete, 85.33% of time used |
| Amount | $6,523,856 revised (original $6,506,472) |
| Paid to date | $6,018,544 |
| Work | Bridge Replacement |
| Location | SH 25, SH 25 to AT MIDDLE FORK LITTLE WICHITA RIVER, Archer County, Wichita Falls District |
| Let / began | 2025-02-06 / 2025-05-19 |
| Latest estimate | 2026-10-02 |
| Contract number | 2253013 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.