# Altus Construction LLC: TxDOT bridge replacement contract 95% complete, IH 40, Carson County ($9,901,873, 10 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Altus Construction LLC |
| Subcontractors | Emery Sapp & Son's INC. (0.16%); Choctaw Erectors, INC. (3.77%); Lindamood, INC. (1.6%); Bryer Paving, L.L.C (0.21%); Crossbar Logistics LLC (0.35%); Square Contracting INC (8.09%); Toro Bravo Construction, LLC (0.9%); Dk Contracting, LLC (0.24%); Osgar Concrete LLC (2.51%); Trp Construction Group, LLC (0.19%) |
| Progress | 95.01% complete, 99.57% of time used |
| Amount | $9,901,873 revised (original $9,874,035) |
| Change orders | $22,838 |
| Paid to date | $9,403,506 |
| Work | Bridge Replacement |
| Location | IH 40, AT IH 40 to ., Carson County, Amarillo District |
| Let / began | 2025-02-07 / 2025-07-07 |
| Latest estimate | 2026-10-05 |
| Contract number | 2253206 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.