# Anderson Columbia Co., INC.: TxDOT interchange (new or reconstructed) contract 39% complete, SL 20, Webb County ($50,601,761, 13 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Anderson Columbia Co., INC. |
| Subcontractors | Houston Sawing & Drilling (0.05%); Weber-Balke Foundation Company, INC (0.66%); Highway Barricades And Services, LLC (1.07%); J. H. Oden Contracting Company (0.51%); Scott Derr Painting Co, LLC (0.32%); K. L. Durham Construction, L.L.C. (0.29%); Scr Civil Construction, LLC (0.3%); Southwest Road & Safety Contractors, LTD. (1.59%); Triple H Field Services, LLC (4.32%); James Construction Group, LLC (27.48%); Texas Icon Construction, LLC (3.14%); Acee Construction LLC. (3.12%); Rio Grande Rebar Rodbusters, LLC (0.45%) |
| Progress | 38.58% complete, 44.53% of time used |
| Amount | $50,601,761 revised (original $49,586,907) |
| Change orders | $1,014,855 |
| Paid to date | $19,523,658 |
| Work | Interchange (New Or Reconstructed) |
| Location | SL 20, 0.580 MILES SOUTH OF LOMAS DEL SUR to 0.721 MILES NORTH OF LOMAS DEL SUR, Webb County, Laredo District |
| Let / began | 2024-11-06 / 2025-07-21 |
| Latest estimate | 2026-10-05 |
| Contract number | 11243003 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.