# Anderson Columbia Co., INC.: TxDOT interchange (new or reconstructed) contract 73% complete, FM 1472, Webb County ($4,125,144, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Anderson Columbia Co., INC. |
| Subcontractors | 4e Tree Worx LLC (0%); K. L. Durham Construction, L.L.C. (1.12%); Highway Barricades And Services, LLC (5.87%); Texas Icon Construction, LLC (0%) |
| Progress | 73.14% complete, 66.15% of time used |
| Amount | $4,125,144 revised (original $3,866,338) |
| Change orders | $258,806 |
| Paid to date | $3,017,035 |
| Work | Interchange (New Or Reconstructed) |
| Location | FM 1472, 2.46 MILES SOUTH OF SH 255 INTERSEC to 4.49 MILES SOUTH OF SH 255 INTERSEC, Webb County, Laredo District |
| Let / began | 2025-12-02 / 2026-02-20 |
| Latest estimate | 2026-10-05 |
| Contract number | 12253022 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.