# Anderson Columbia Co., INC.: TxDOT widen freeway contract 100%+ complete, SH 141, Jim Wells County ($24,817,198, 9 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Anderson Columbia Co., INC. |
| Subcontractors | Rio Grande Rebar Rodbusters, LLC (0%); Munoz Foundation Drilling, INC. (0%); Highway Barricades And Services, LLC (2.88%); Soil Tech Advance INC. (0.65%); G & E Escobedo Construction, INC. (0%); *austin Traffic Signal Construction Co., INC. (1.49%); Foremost Paving, INC. (3.91%); Performance Equipment Service (0.42%); Texas Icon Construction, LLC (0.37%) |
| Progress | 104.06% complete, 97.91% of time used |
| Amount | $24,817,198 revised (original $24,833,825) |
| Change orders | $-16,627 |
| Paid to date | $25,825,919 |
| Work | Widen Freeway |
| Location | SH 141, US 281 to KLEBERG COUNTY LINE, Jim Wells County, Corpus Christi District |
| Let / began | 2024-01-04 / 2024-05-13 |
| Latest estimate | 2026-10-02 |
| Contract number | 1243003 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.