# Anderson Columbia Co., INC.: TxDOT convert non-freeway to freeway contract 74% complete, US 77, Kleberg County ($186,117,106, 19 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Anderson Columbia Co., INC. |
| Subcontractors | Highway Barricades And Services, LLC (0.42%); Highway Pavement Specialties, INC. (0%); Hunter Demolition & Wrecking Corporation (0.08%); J. H. Oden Contracting Company (0.33%); Jb Pinnacle Group, LLC (0.88%); Pinnacle Grinding And Grooving LLC (0.01%); Reim Construction, INC. (7.4%); Traf-Tex, INC. (1.95%); Southwest Road & Safety Contractors, LTD. (0.29%); Scott Derr Painting Co, LLC (0.09%); Rio Grande Rebar Rodbusters, LLC (0%); Foremost Paving, INC. (31.07%); Flovera Construction Services, LLC (3.92%); Primate Construction, LP (0.04%); 2j Resources, LLC (1.4%); Texas Icon Construction, LLC (1.23%); J. Carroll Weaver, INC. (0.13%); Houston Sawing & Drilling (0%); Zamco Directional Drilling LLC (0%) |
| Progress | 73.94% complete, 61.1% of time used |
| Amount | $186,117,106 revised (original $176,703,809) |
| Change orders | $4,365,984 |
| Paid to date | $133,878,452 |
| Work | Convert Non-Freeway To Freeway |
| Location | US 77, CR 2130 to 1.5 MI. N. OF SH 285, Kleberg County, Corpus Christi District |
| Let / began | 2022-03-03 / 2022-10-03 |
| Latest estimate | 2026-10-02 |
| Contract number | 3223002 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.