# Anderson Columbia Co., INC.: TxDOT interchange (new or reconstructed) contract 100%+ complete, SH 35, Aransas County ($22,974,054, 13 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Anderson Columbia Co., INC. |
| Subcontractors | Island Construction, L.P. (0.64%); Epic Energy Services LLC (0.43%); Doran Steel, INC. (0.17%); Texas Icon Construction, LLC (0.17%); Highway Barricades And Services, LLC (1.43%); Traf-Tex, INC. (1.36%); M & D Foundation Drilling Industries, INC. (3.5%); Toro Bravo Construction, LLC (0%); Flovera Construction Services, LLC (8.66%); Primate Construction, LP (0.06%); Aaron Concrete Contractors, LLC (1.02%); K. L. Durham Construction, L.L.C. (0.34%); Brooke Paving And Construction LLC (0.18%) |
| Progress | 100.07% complete, 151.91% of time used |
| Amount | $22,974,054 revised (original $22,334,444) |
| Change orders | $454,917 |
| Paid to date | $22,804,255 |
| Work | Interchange (New Or Reconstructed) |
| Location | SH 35, ON SH35 AT CORPUS CHRISTI ST. INTER to ., Aransas County, Corpus Christi District |
| Let / began | 2023-03-08 / 2023-05-22 |
| Latest estimate | 2026-10-02 |
| Contract number | 3233204 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.