# Anderson Columbia Co., INC.: TxDOT convert non-freeway to freeway contract 69% complete, US 281, Jim Wells County ($140,487,953, 14 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Anderson Columbia Co., INC. |
| Subcontractors | Highway Barricades And Services, LLC (0.77%); A. H. Beck Foundation Co., INC. (2.15%); Primate Construction, LP (0.09%); Professional Traffic Control LLC (0.01%); Rio Grande Rebar Rodbusters, LLC (0%); Texas Icon Construction, LLC (1.22%); Traf-Tex, INC. (3.49%); Russo Corporation (0%); A.Z. Rebar Construction, INC. (0%); Acee Construction LLC. (1.26%); Jb Pinnacle Group, LLC (1.01%); Eggemeyer Land Clearing, LLC (0.18%); Flovera Construction Services, LLC (2.41%); Foremost Paving, INC. (16.54%) |
| Progress | 69.47% complete, 65.59% of time used |
| Amount | $140,487,953 revised (original $138,438,663) |
| Change orders | $490,943 |
| Paid to date | $96,514,558 |
| Work | Convert Non-Freeway To Freeway |
| Location | US 281, BU 281 R N. OF ALICE to SH 44, ETC., Jim Wells County, Corpus Christi District |
| Let / began | 2023-06-01 / 2024-01-02 |
| Latest estimate | 2026-10-02 |
| Contract number | 6233001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.